🔨🔥 ONGOING PROJECT | SERIOUS FLOOR PREPARATION 🔥🔨
Another one underway, and this floor definitely needed some serious preparation before we can get anywhere near the finished floor! 💪🏼🛠️
We started with 4 large channels ranging from 20–30mm deep 🕳️📏, which were filled using rapid repair mortar to bring everything back up and provide a solid, stable base. 💪🏼
The new extension was then DPM’d 💧🖤, ready for the next stages of preparation. The following day we attacked the lower areas with a 30mm build-up of self-levelling compound and Granite 🪣⚒️, bringing the levels up significantly.
We then moved onto the existing floorboards, installing 6mm plywood 🪵🔩 before applying a further 10mm build-up coat of screed, bringing the floor level up to the plywood. 📐👌🏼
The whole floor is now being prepared ready for the final 5mm coat all over 🪣✨, giving us the perfect, smooth substrate required for the finished flooring. 🔥
This one is still VERY MUCH A WORK IN PROGRESS 👀🚧…
So keep your eyes peeled for the next stage! 👁️🔥
➡️ The perfect self-level finish 😍
➡️ Followed by a brand-new herringbone installation 🪵🔶🔥
It’s going to be a good one! 😆💪🏼