A loading dock addition can add six to twelve months to a project schedule.
The construction isn't what causes the delay. Adding square footage, even something as routine as an enclosed loading dock, can trigger a planning board review and new parking calculations, even when the number of people in the building doesn't change.
Warehouses face the same kind of threshold with fire protection. Changing what you store, or even how it's packaged, can change your commodity classification and trigger sprinkler upgrades without any physical construction.
Early code and zoning analysis puts these thresholds on the table before you set a budget, so they show up in the plan instead of in the change orders.